Construction log

Construction log

What happened on the site and when, from the tree's first survey to the handover.

The floors poured so far.

2026

  1. The yearly survey

    The tree's yearly survey: healthy leaves. Two low branches were pruned before the sixth floor is poured.

  2. The fifth floor

    The fifth-floor slab. The windows for the lower floors arrived on site.

  3. The fourth floor

    The fourth-floor slab is poured. The sycamore is fenced and watered every week.

  4. The third floor

    The third-floor slab.

  5. The first floors

    The first- and second-floor slabs.

  6. The ground floor

    The ground-floor slab. The lobby takes shape; the wall to the tree stays open.

2025

  1. Foundations

    Piles on the west side, and beams that bridge the roots on the east.

  2. A fence and water

    A fence at 9 metres round the sycamore, and water once a week. Digging starts on the west side.

  3. The permit

    The building permit.

2024

  1. The plan moves

    The building six metres west, the basement out from under the crown.

  2. The tree survey

    14 metres tall, a crown 22 metres wide, about a hundred years old. The advice: touch nothing within 9 metres.

Planned

To the handover

  1. December 2026The sixth-floor slab.
  2. April 2027The frame is done, the facades begin.
  3. October 2027Windows, plaster and the flats' finish.
  4. January 2028The garden and the lobby. The fence round the tree comes down.
  5. Spring 2028Handover.